Business
Self-Generation or Distributed Generation: Which Regulatory Category Fits Your Company's Solar Project
When a company decides to install solar, the first technical question is not which panel to buy but under which regulatory category the plant will operate. In Colombia the same technology can connect as small-scale self-generation, large-scale self-generation, distributed generation, remote self-generation or collective self-generation, and each category brings its own connection procedure, its own way of settling the energy delivered to the grid and its own requirements on who may carry it out. Choosing wrongly is not a paperwork mistake: it changes what each kWh leaving the plant is worth. This article explains what sets each one apart, under the regulation in force in October 2026, and how to decide which one fits a company's project.
13 min read Published on
In short
A company that installs solar to consume its own energy is a self-generator. If installed capacity is up to 1 MW, it is a small-scale self-generator (AGPE, Resolución UPME 281 de 2015) and, with renewable sources, its surplus is recognised as an energy credit under Resolución CREG 174 de 2021. Above 1 MW it is a large-scale self-generator (AGGE): it is governed by Resolución CREG 024 de 2015 and Decreto 1073 de 2015, and to export surplus it must be represented in the wholesale market by a retailer or a generator; the price comes from that contract. Distributed generation is something else: it is carried out by a public utility company that sells all the energy from a plant under 1 MW connected to the distribution grid. If the plant does not export to the grid, there is no capacity limit and no scale distinction, although RETIE and the connection procedure still apply.
Key points
- Self-generating means producing energy mainly for one's own consumption; the company does not have to own the equipment, so an on-site PPA is still self-generation.
- The line between small and large scale is 1 MW of installed capacity (Resolución UPME 281 de 2015). Below it, AGPE; above it, AGGE.
- An AGPE using renewables receives an energy credit for its surplus up to what it imports in the period; an AGGE sells its surplus through a retailer or generator that represents it, at the price set in that contract.
- Distributed generation is not self-generation: it is carried out by a public utility company (ESP) that sells all the energy from a plant under 1 MW. A company that only wants to cut its bill is not a distributed generator.
- Without exports to the grid there is no capacity limit and no scale distinction (Decreto 1403 de 2024), but RETIE and the connection procedure with the grid operator still apply.
- Since 2026 CREG regulates remote self-generation (Resolución CREG 101 099 de 2026): producing at one site and consuming at another over the grid, with its own rules and charges.
- The practical decision rests on three facts: installed capacity, whether there will be surplus, and whether consumption is at the same point where the energy is generated.
Why the category matters before the panel
The regulatory category defines three things that weigh on the return of a business project: which connection procedure the grid operator requires and how long it takes, how the energy the plant delivers to the grid when the company does not consume it is paid, and who must act in the electricity market for that energy to be settled.
Categories are not chosen by preference. They follow from facts about the project: the plant's installed capacity, whether energy will be exported to the grid and where the consumption served by the plant is located. That is why those three facts should be fixed at the start of the design, not at the end, once the proposal is signed.
Self-generation: producing for your own consumption
Resolución CREG 174 de 2021 defines self-generation as the activity of users, individuals or legal entities, who produce electricity mainly to meet their own needs. When they serve their own demand they do so without using distribution or transmission assets; the grid is used to deliver surplus and as backup.
One detail of the definition matters a great deal to companies: the self-generator may or may not own the generation assets. If a third party installs, finances and operates the plant on the company's roof and sells it the energy (the on-site PPA model), the company is still the self-generator. Financial structure and regulatory category are separate decisions.
Within self-generation, size separates two regimes. Resolución UPME 281 de 2015 sets the small-scale limit at 1 MW, measured as the installed capacity of the generation system.
AGPE: up to 1 MW, with an energy credit
A small-scale self-generator (AGPE) has installed or nominal capacity of up to 1 MW. It is the category of almost every rooftop project for shops, offices, mid-sized plants and agribusiness, and the one regulated in detail by Resolución CREG 174 de 2021, as amended by Resolución CREG 101 072 de 2025 and Resoluciones CREG 101 097, 101 099 and 101 113 de 2026.
For an AGPE using non-conventional renewable sources, such as solar, the surplus delivered to the grid is recognised as an energy credit up to the amount imported in the period, and anything above that is valued hour by hour (article 25). The retailer charges for each kWh swapped: up to 100 kW, the retail component; above 100 kW and up to 1 MW, the sum of transmission, distribution, retail, losses and constraints.
The connection procedure also scales with size. An AGPE exporting surplus with more than 100 kW needs a simplified connection study; up to 100 kW, or without exports, it does not. The application is filed in the grid operator's online system, and Resolución CREG 101 113 de 2026 gave the current text of article 14, which lists the application documents.
An AGPE using renewables has one more advantage the large-scale self-generator lacks: Decreto 929 de 2023 exempts it from reactive energy charges (paragraph 2 of article 2.2.3.2.4.9 of Decreto 1073 de 2015, added by that decree). In an industrial plant with motors and compressors, that difference can matter when deciding whether to stay below 1 MW.
AGGE: above 1 MW, with a market representative
Above 1 MW of installed capacity, the company is a large-scale self-generator (AGGE). Its regime is set by Resolución CREG 024 de 2015, which regulates large-scale self-generation in the National Interconnected System, and, for connection to the distribution grid, by Resolución CREG 174 de 2021 when the declared maximum power is under 5 MW.
The commercial difference is the most important one. The energy credit in Resolución CREG 174 de 2021 is written for the AGPE; the AGGE does not have it. To export surplus, Decreto 1073 de 2015, as worded by Decreto 1403 de 2024, requires it to be represented in the wholesale market by a retail agent or a generation agent. The value of each exported kWh comes from that contract, not from a regulated formula, so the installer's proposal should state which representative and which terms it assumed.
On the procedure, Ley 1715 de 2014 ordered a simplified process for AGGEs exporting less than 5 MW. Resolución CREG 174 de 2021 develops it: a simplified connection study, a guarantee the rule applies to AGGEs with declared maximum power between 1 and 5 MW, and a connection approval whose validity can be extended only once and on listed grounds. Above 5 MW, or when connecting to the regional or national transmission system, the project falls outside that resolution and follows the rules for a generation plant of similar capacity.
The AGGE must also sign a backup contract with the grid operator or transmitter it connects to (Decreto 1073 de 2015, as worded by Decreto 1403 de 2024); for an AGPE that contract is optional. The backup charge is calculated under the regulation and the financial model should include it.
If the plant does not export to the grid
Many business plants are designed so that all output is consumed on site, with zero-export control. In that case Decreto 1403 de 2024 provides that no authorisation of any kind is needed for the connection, that there is no distinction between large and small scale and that there are no capacity limits.
That does not mean there is no procedure. CREG has stated that a self-generator without surplus must comply with the regulation in force, RETIE and the connection procedure with the grid operator, and under Resolución CREG 174 de 2021 self-generators without exports connected to the distribution system follow the procedure without a simplified connection study. It is the fastest route, at the cost of giving up the value of the surplus.
The decision has a design consequence: without exports, the plant is sized against the minimum consumption during sunlight hours, not the average, and output on weekends or holidays with the facility idle is lost. The more stable the daytime load, the less is sacrificed.
Distributed generation: a sales business, not self-consumption
Distributed generation is often confused with self-generation, but in Colombian regulation it is a different activity. Resolución CREG 174 de 2021 defines it as generating electricity with a plant of installed capacity under 1 MW, located close to consumption centres and connected to the Local Distribution System. Whoever carries it out, the distributed generator (GD), is a public utility company and, for all purposes, a generation agent subject to the rules of that activity.
The GD does not consume its energy: it sells it. It can sell under the general market rules or directly to the retailer integrated with the grid operator, which is obliged to buy it at a price regulated by article 22 of that resolution, as amended by Resolución CREG 101 072 de 2025.
For a company that wants to cut its bill, this category is almost never the right one: it requires becoming a public utility company and operating as a generator. It makes sense for those who want to turn energy sales into a business, for example with a large roof and little own consumption, and even then it is worth comparing with leasing the roof to a third party who develops the project.
Remote self-generation and energy communities
Two newer categories widen the map. The first is remote self-generation: producing at one site and consuming at another over the grid. Decreto 1403 de 2024 set the policy and Resolución CREG 101 099 de 2026 regulated it: the remote self-generator is not subject to the 1 MW small-scale limit, pays the backup and network charges set by the regulation, and its generation asset connects under rules equivalent to those of a plant of its size (those under 5 MW, under Resolución CREG 174 de 2021). It is the category for a company without a usable roof, or with several sites, that wants energy from its own plant elsewhere.
The second is energy communities, created by Decreto 2236 de 2023 and regulated by Resolución CREG 101 072 de 2025: collective self-generation (several users producing for their own demand) and collective distributed generation, within the power and dispersion limits set by Resolución UPME 501 de 2024 (under 5 MW). In its Concepto 14037 de 2025, CREG stated that a legal entity with several commercial metering points can form an energy community. For an industrial park or a group of neighbouring companies it is an option worth studying, bearing in mind that its regulation is recent.
How to decide: four questions
Four answers identify the category of almost any business project. They are questions to settle with the installer at the design stage, with the hourly load profile on the table.
- Will the plant export energy to the grid? If not, there is no capacity limit or scale distinction and the procedure is the simplest; if so, go to the second question.
- Does installed capacity exceed 1 MW? Up to 1 MW it is an AGPE, with an energy credit and the reactive energy exemption; above it, an AGGE, with a market representative, the guarantee and extension rules up to 5 MW and a mandatory backup contract.
- Is consumption at the same connection point as the plant? If not, the category is remote self-generation or, among several users, collective self-generation.
- Is the goal to sell energy rather than consume it? Then the conversation is about distributed generation, which requires being a public utility company, or about leasing the roof to a third party.
The 1 MW threshold
Companies with large loads often find that their optimal plant is somewhat above 1 MW. Before crossing the threshold it is worth comparing two scenarios: a plant of up to 1 MW as an AGPE, with the energy credit and the reactive energy exemption of Decreto 929 de 2023, and a larger plant as an AGGE, with more output but with surplus valued by contract, the guarantee rules and the mandatory backup contract.
There is no general answer: it depends on how much of the output is self-consumed and on what the representative offers for the surplus. If the larger plant barely exports, the commercial difference matters little; if it exports a lot, it matters a great deal. What should be avoided is finding out afterwards, because the capacity declared in the procedure fixes the category.
In both cases the same technical safety requirements apply: RETIE as currently in force, with the text of the four books issued by Resolución 40284 de 2026, which requires full certification for self-generation of 10 kVA or more that exports surplus, and the agreements of the National Operation Council (CNO) on protection and testing for the connection.
Found this useful? Add us as a preferred source in Google.
Sources: Resolución CREG 174 de 2021 (net metering regulation) (opens in a new tab) · Resolución CREG 101 072 de 2025 (amends the net metering regulation) (opens in a new tab) · Resolución CREG 101 099 de 2026 (remote self-generation) (opens in a new tab) · Resolución CREG 101 113 de 2026 (battery storage; current text of article 14 of Resolución CREG 174) (opens in a new tab) · Resolución UPME 281 de 2015 (1 MW limit for small-scale self-generation) (opens in a new tab) · Resolución CREG 024 de 2015 (large-scale self-generation) (opens in a new tab) · Ley 1715 de 2014 (Renewable Energy Law) (opens in a new tab) · Decreto 1403 de 2024 (remote self-generation policy) (opens in a new tab) · Decreto 929 de 2023 (energy policy; reactive-energy exemption for small-scale self-generators) (opens in a new tab) · Decreto 2236 de 2023 (energy communities) (opens in a new tab) · Resolución UPME 501 de 2024 (capacity limits for energy communities) (opens in a new tab) · RETIE — Resolución 40284 de 2026, amending the regulation adopted by Resolución 40117 de 2024 (electrical installations) (opens in a new tab) · Acuerdo CNO 2233 de 2026 (protection requirements for connecting generation) (opens in a new tab) · Acuerdo CNO 2229 de 2026 (tests for connecting generators under 5 MW) (opens in a new tab)
Frequently asked questions
Can my company be a self-generator if a third party owns the plant?
Yes. Resolución CREG 174 de 2021 expressly states that the self-generator may or may not own the generation assets. In an on-site PPA the third party owns the equipment and the company remains the self-generator before the grid operator.
Where is the line between small and large scale?
At 1 MW of installed capacity, under Resolución UPME 281 de 2015. Up to that value the project is an AGPE; above it, an AGGE. If the plant does not export to the grid, Decreto 1403 de 2024 removes the scale distinction and the capacity limits.
Can an AGGE sell its surplus?
Yes, but not with an energy credit. Under Decreto 1073 de 2015, as worded by Decreto 1403 de 2024, it must be represented in the wholesale market by a retail agent or a generation agent, and the value of the surplus comes from that contract. Resolución CREG 024 de 2015 regulates the rest of the activity.
What is the difference between self-generation and distributed generation?
A self-generator produces mainly for its own consumption and exports only the surplus. A distributed generator is a public utility company that sells all the energy from a plant under 1 MW connected to the distribution grid. For a company that wants to save on its bill, the usual category is self-generation.
Can I generate on a plot of land and consume at my plant elsewhere?
Yes, through the remote self-generation regulated by Resolución CREG 101 099 de 2026, under Decreto 1403 de 2024. The energy travels over the grid, so the network and backup charges set by the regulation apply; it is worth modelling them before comparing with a rooftop plant.
If I do not export surplus, do I skip the grid operator procedure?
No. No authorisation is needed and there is no capacity limit, but RETIE and the connection procedure with the grid operator still apply; in that case no simplified connection study is required.